Logic link
Logic links describe the relationships between one activity and another.
Common types of logic link include:
- Finish-to-start: One activity cannot start until a previous activity has finished.
- Lagged finish-to-start: One activity cannot start until a specific amount of time after a previous activity has finished.
- Start-to-start: One activity cannot start until another activity has started.
- Lagged start-to-start: One activity cannot start until a specific amount of time after another activity has started.
- Finish-to-finish: One activity cannot finish until another activity has finished.
- Lagged finish-to-finish: One activity cannot finish until a specific amount of time after another activity has finished.
- Lagged start and finish: One activity cannot start until a specific amount of time after another activity has started, and it cannot finish until a specific amount of time after that activity has finished.
- Negative lag: One activity can start a specific amount of time before another activity has been completed.
- Must start / must finish. The activity must start or finish on a specific date.
Ref The Society of Construction Law Delay and Disruption Protocol, 2nd edition, published in February 2017 by the Society of Construction Law (UK).
[edit] Related articles on Designing Buildings Wiki
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
CIAT reflects on the party conferences.
CIOB announce the winners of the Art of Building photography competition.
National Scheme of Delegation introduced.
The cost of employing people remains a concern.
Code of Practice for Electrical Energy Storage Systems.
ECA calls on members to comment on draft 4th edition.
Bringing together expertise and creating cultural benefits.
CIOB celebrates positive Ofsted report.
The Building Safety Regulator announces a call for evidence.
Government approach could undermine delivery and regeneration.
World's first mass timber data centre.
The overlooked environmental aspect of data centre development.
Introduction to radon awareness
New technical information sheet published by CIOB.
Updated supplier guide can help electrical contractors engage with NHP.